The following table contains information related to the major activities of a project a. Draw the precedence diagram b. find the critical path c. Determine
The following table contains information related to the major activities of a project a. Draw the precedence diagram b. find the critical path c. Determine the project completion time. Activity Immediate pedecessor Duration 5 A A A 8 2 E 3 F E 6 G G 2 to I B,D J FI 8 K K 17 ACHIDT Mono > | aculwlo