Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Most Likely (m) (b) ABCDEFGHIT None
The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Most Likely (m) (b) ABCDEFGHIT None None A A B E, F G H, I Optimistic (a) 2432SMANGO 5765 on nao 6 5 Pessimistic 8698HSH 16 11 15 14 8 12 (a) Draw the project network. Use activity on node (A-O-N) method. (b) Identify the Critical Path. Calculate the length and variance of the Critical Path (c) Identify the non-critical activities. Work out the Total Slack (TS) and Free Slack (FS) for all the non-critical activities. (d) State whether the network is sensitive or insensitive! (e) What is the approximate probability that jobs on the critical path will be completed by the due date of (i)24 days, (ii) 29 days? (0.50+0.50+0.50+0.50+3.00-5)
Step by Step Solution
★★★★★
3.37 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
ANSWER Activity To Tm Tp Te var05 Var A 4 8 10 7666667 1 1 B 2 8 24 9666667 36...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started