The following table of probabilistic time estimates ( in weeks ) and activity predecessors are provided for a project. Activity optimistic time most likely time
The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project.
Activity
optimistic
time
most likely
time
pessimistic
time
Activity Predecessor
A
B
A
C
A
D
B C
E
D
Table
Reference: Ref
Using Table the expected time to complete the project is
A weeks.
B weeks.
C weeks.
D weeks.QUESTION
The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project.
Activity
optimistic
time
most likely
time
pessimistic
time
Activity Predecessor
A
B
A
C
A
D
B C
E
D
Table
Reference: Ref
Using Table the expected time to complete the project is
A weeks.
B weeks.
C weeks.
D weeks.QUESTION
The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project.
Activity
optimistic
time
most likely
time
pessimistic
time
Activity Predecessor
A
B
A
C
A
D
B C
E
D
Table
Reference: Ref
Using Table the expected time to complete the project is
A weeks.
B weeks.
C weeks.
D weeks.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started