The following table represents a plan for a project: JOB NUMBER PREDECESSOR JOB ( S ) TIMES ( DAYS ) a m b 1 2

The following table represents a plan for a project:
JOB NUMBER PREDECESSOR JOB(S) TIMES (DAYS)
a m b
1234
21123
314512
413411
52135
63123
74189
85,6246
982412
107345
119,10578
b. Indicate the critical path.
multiple choice 1
1-4-7-10-11
1-2-5-8-9-11
1-3-6-8-9-11
c. What is the expected completion time for the project?
Note: Do not round intermediate calculations. Round your answer to 2 decimal places.
d. You can accomplish any one of the following at an additional cost of $1,500. If you will save $1,000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?
Reduce job 5 by two days.
multiple choice 2
Yes
No
Reduce job 3 by two days.
multiple choice 3
Yes
No
Reduce job 7 by two days.
multiple choice 4
Yes
No
e. What is the probability that the project will take more than 30 days to complete?
Note: Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Other than the expected completion time you entered in part c above, do not round intermediate calculations. Round "z" value to 2 decimal places and your final answer to 4 decimal places

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

High Output Management

Authors: Andrew S. Grove

2nd Edition

9780679762881

More Books

Students also viewed these General Management questions

Question

Explain how labour relations practices differ around the world.

Answered: 1 week ago