Question

1 Approved Answer

The following table represents a plan for a project: TIMES (DAYS) PREDECESSOR JOB NO. JOB(S) a m b 1 2 3 4 2 1

image text in transcribedimage text in transcribed

The following table represents a plan for a project: TIMES (DAYS) PREDECESSOR JOB NO. JOB(S) a m b 1 2 3 4 2 1 1 2 3 3 1 4 5 12 4 1 3 4 11 5 2 1 3 5 6 3 1 2 3 7 4 1 8 9 8 5,6 2 4 6 9 8 2 4 12 10 11 7 3 4 5 9, 10 5 7 8 b. Indicate the critical path. O1-2-5-8-9-11 1-3-6-8-9-11 O1-4-7-10-11 c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Expected completion time days e. What is the probability that the project will take more than 30 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Other than the expected completion time you entered in part c above, do not round intermediate calculations. Round "z" value to 2 decimal places your final answer to 4 decimal places.) Probability

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions

Question

3. Give short, clear directions before, not during, transitions.

Answered: 1 week ago

Question

55. Microsoft has five/5 business divisions.

Answered: 1 week ago