Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following table shows a Project Budget Baseline. At the end of week 20 this project has cost $41,000. It has an earned value as
The following table shows a Project Budget Baseline. At the end of week 20 this project has cost $41,000. It has an earned value as indicated in the table as a % complete for each activity at the end of week 20. Use the data to answer the following questions about the status of the project at the end of week 20.
a. Find the cost and schedule variances.
b. Find CPI and SPI of the project using earned value calculations.
c. Assuming performance continues at the current rate, calculate the ETC, EAC, and VAC for the project.
Activity Duration % Complete 5 10 15 20 25 Conceptual Design $5,000 $3,000 100% Graphics Design $6,000 $3,000 $2,000 100% Copyright $2,000 $3,000_$3,000_85% Samples $1,000 $2,000 90% Tooling $2,000 $2,000_ $2,000_50% Production $4,000 $3,000_$7,000 15% Total $5,000 $9,000_$12,000 $12,000 $12,000 Cumulative Total $5,000 $14,000 $26,000 $38,000 $50,000 Activity Duration % Complete 5 10 15 20 25 Conceptual Design $5,000 $3,000 100% Graphics Design $6,000 $3,000 $2,000 100% Copyright $2,000 $3,000_$3,000_85% Samples $1,000 $2,000 90% Tooling $2,000 $2,000_ $2,000_50% Production $4,000 $3,000_$7,000 15% Total $5,000 $9,000_$12,000 $12,000 $12,000 Cumulative Total $5,000 $14,000 $26,000 $38,000 $50,000Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started