The following table shows the activities for a project. TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSOR(S) NORMAL CRASH NORMAL CRASH AVAILABLE WEEKS OF CRASHING CRASHING

  1. The following table shows the activities for a project.

TIME (WEEKS)

COST ($)

ACTIVITY

IMMEDIATE PREDECESSOR(S)

NORMAL

CRASH

NORMAL

CRASH

AVAILABLE WEEKS OF CRASHING

CRASHING COST / WEEK

A

Start

3

2

3,000

3,300

B

Start

6

4

8,000

9,000

C

A

1

1

4,000

4,000

D

A

5

4

3,500

4,000

E

B

4

3

4,750

5,500

F

C

2

2

2,000

2,000

G

D

1

1

4,000

4,000

H

D,F

3

2

3,500

3,750

I

E,G

3

2

3,000

4,250

J

E

2

1

5,000

7,000

Finish

H, I, J

--

--

--

--

    1. Draw the network diagram.
    2. What is the critical path for the project using the normal time?
    3. Complete the table by filling the missing information.
    4. How many week(s) of crashing are available for activity E?
    5. Which activity should be crashed first?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions