The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities: Activity O (Optimistic time) M (Most likely

The following table shows three time estimate (Optimistic, Pessimistic, and Most likely) of a project with 5 activities:

Activity

O (Optimistic time)

M (Most likely time)

P (Pessimistic time)

Immediate Predecessor

A

1

3

6

-

B

3

4

5

A

C

2

4

6

B

D

6

9

10

A, C

E

2

6

10

D

Conduct a PERT analysis and find the critical path of the project.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Wildlife Ecology Conservation And Management

Authors: Anthony R. E. Sinclair, John M. Fryxell, Graeme Caughley

2nd Edition

1405107375, 978-1405107372

More Books

Students also viewed these General Management questions

Question

I was partially responsible.

Answered: 1 week ago