The forecasted demand in aggregate units for April is given as 4XXX. You need to replace XXX with the last 3 digits of your Student

The forecasted demand in aggregate units for April is given as 4XXX. You need to replace XXX with the last 3 digits of your Student ID number. For example, if your student ID number is 105987, you will use a forecasted value of 4987 microwave ovens for April.

A normal work-day is eight hours. Hiring costs are OMR 650 per worker and firing costs are OMR 1950 per worker. Holding costs are OMR 5 per aggregate unit held per month, and backorder cost is OMR 45 per aggregate unit per month. It requires an average of 50 minutes for one worker to assemble one oven. The ending inventory in December of the previous year was 225 units, and the manager wants to have at least 120 units on hand in inventory at the end of June. The workforce at the end of December in the previous year was 20 workers. Workers are paid OMR 6 per hour for regular time labor. Overtime labor costs OMR 9 per worker per hour, and the maximum overtime that is allowed is 3 hours per worker each day.

(a) Find the minimum constant workforce plan for the six months and the total cost of the plan. The firm does not want any stockouts. The plan should show the production levels, workforce levels, number hired, number fired, ending inventory and shortages for each month. You may hire or fire workers only at the beginning of January. What is the cost of this plan?

(b) Determine the zero inventory (chase) plan that hires and fires workers each month to match demand as closely as possible, and the cost of that plan. No stockouts are allowed.

(c) Prepare an Excel sheet to generate the aggregate production plan for part (b). Use this Excel sheet to find the total cost if the forecast demand for February is changed to 3500 microwave ovens.

(d) Formulate the problem as a linear programming model to find the best aggregate production plan.

(e) Use Excel Solver to find a feasible aggregate production plan through the conservative approach. Explain.

MonthWorkdaysForecasted demand
Jan223325
Feb183940
Mar234825
Apr204987
May234780
June194425

Step by Step Solution

3.39 Rating (149 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Macroeconomics

Authors: Robert J Gordon

12th edition

138014914, 978-0138014919

More Books

Students also viewed these Electrical Engineering questions

Question

Write each number in scientific notation. 0.875

Answered: 1 week ago

Question

When may a taxpayer petition the U.S. Tax Court? How is this done?

Answered: 1 week ago