Question

1 Approved Answer

The Gantt chart of Project X included 12 consecutive tasks. Each task was supposed to take 1 month and to cost $115,000. After 6 months

The Gantt chart of Project X included 12 consecutive tasks. Each task was supposed to take 1 month and to cost $115,000. After 6 months tasks 1-5 were completed, task 6 was 50% completed, and the project had spent $650,000. EV=500,000.

1. Determine the Estimated budget at completion = Original Budget/ CPI and Estimated time to complete = Original Time Estimate /SPI.

image text in transcribed

EVM formulas EV=PV*Rate of Completion (%) Performance indicators CV=EV - AC SV=EV - PV CPI = EVIAC SPI = EV/PV Forecasts Estimated budget at completion = Original Budget/ CPI Estimated time to complete = Original Time Estimate /SPI

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Managerial Accounting

Authors: Peter C. Brewer, Ray H. Garrison, Eric Noreen, Suresh Kalagnanam, Ganesh Vaidyanathan

5th Canadian edition

77429494, 1259105709, 1260480798, 978-1259105708

Students also viewed these Accounting questions