The Gantt chart of Project X included 12 consecutive tasks. Each task was supposed to take 1 month and to cost $115,000. After 6 months
The Gantt chart of Project X included 12 consecutive tasks. Each task was supposed to take 1 month and to cost $115,000. After 6 months tasks 1-5 were completed, task 6 was 50% completed, and the project had spent $650,000. EV=500,000.
1. Determine the Estimated budget at completion = Original Budget/ CPI and Estimated time to complete = Original Time Estimate /SPI.
EVM formulas EV=PV*Rate of Completion (%) Performance indicators CV=EV - AC SV=EV - PV CPI = EVIAC SPI = EV/PV Forecasts Estimated budget at completion = Original Budget/ CPI Estimated time to complete = Original Time Estimate /SPI
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started