Question

1 Approved Answer

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction should start Oct 1, 2023 and finish

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction should start Oct 1, 2023 and finish before Dec 1, 2025. Ben Keith, the president of tcompany, expressed optimism at obtaining the contract and revealed that the company could net he as much as $2,000,000 on the project. He also said if they are successful, the prospects for future projects are quite good, since there is a projected renaissance in building classic ball parks with modern luxury boxes. Given the information provided in the worksheet titled Question 2, complete the following tasks: a) Construct an AON (Activity on Node) network and a Gantt chart in Excel and find the ES EF LS and LF values. b) Identify the critical path. How many days does the project take to be completed? Which activities have slacks and how may days? c) Provide a deadline that the company can finish this project by. If they cannot finish the project by the deadline you provided, there will be a penalty of $10,000 per day. Assume that the crew works seven days a week and they always find workers to work during holidays. d) What if the durations of the activities D, F, and Q double? How does that affect the project completion time? Provide a short discussion. e) Based on the schedule would you recommend that G&E pursue this contract? Why?

ID Activity Duration (weeks) Predecessors
A Clear Stadium Site 10 None
B Demolish Building 5 A
C Set Up Construction Site 10 B
D Drive Support Piles 18 A
E Pour Lower Concrete Bowl 18 D
F Pour Main Concourse 18 B,E
G Install Playing Field 13 B,E
H Construct Upper Steel Bowl 18 B,E
I Install Seats 20 F,H
J Build Luxury Boxes 13 F,H
K Install Jumbotron 5 F,H
L Stadium Infrastructure 18 F,H
M Construct Steel Canopy 11 I
N Light Installation 5 M
O Build Roof Supports 13 E
P Construct Roof 26 O
Q Install Roof Tracks 13 O
R Install Roof 13 P,Q
S Inspection 3 G,J,L,N,R

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

Prove that ex+y = exey for every x, y .

Answered: 1 week ago

Question

15-5 How will MIS help my career?

Answered: 1 week ago

Question

consumers was surveyed and

Answered: 1 week ago