Question
The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be
The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes.
ASSIGNMENT
Given the information provided in Table below, construct a network schedule for the stadium project and answer the following questions:
1. Will the project be able to be completed by the May 20 deadline? How long will it take?
2. What is the critical path for the project?
3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.
ID | Task Name | Duration | |
1 | Baseball Stadium | ||
2 | Clear stadium site | 70 days | - |
3 | Demolish building | 30 days | 2 |
4 | Set up construction site | 70 days | 3 |
5 | Drive support piling | 120 days | 2 |
6 | Pour lower concrete bowl | 120 days | 5 |
7 | Pour main concourse | 120 days | 3,6 |
8 | Install playing field | 90 days | 3,6 |
9 | Construct upper steel bowl | 120 days | 3,6 |
10 | Install seats | 140 days | 7,9 |
11 | Build Luxury boxes | 90 days | 7,9 |
12 | Install jumbotron | 30 days | 7,9 |
13 | Stadium infrastructure | 120 days | 7,9 |
14 | Construct steel canopy | 75 days | 10 |
15 | Light installation | 30 days | 14 |
16 | Build roof supports | 90 days | 6 |
17 | Construct roof | 180 days | 16 |
18 | Install roof tracks | 90 days | 16 |
19 | Install R roof | 90 days | 17,18 |
20 | Inspection | 20 days | 8,11,13,15,19 |
For purposes of this case assume the following:
1. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
3. The construction crew work Monday through Friday.
Step by Step Solution
3.48 Rating (148 Votes )
There are 3 Steps involved in it
Step: 1
The program evaluation and review technique also known as PE...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started