The general manger of a distribution centre has asked you to manage a project which will see the construction of a warehouse loading dock. You
The general manger of a distribution centre has asked you to manage a project which will see the construction of a warehouse loading dock. You have identified 9 major activities for the project. The cost and duration of each activity are shown in the following table.
Activity | Preceding Activity(s) | Duration (months) | Cost ($000s) |
A | - | 1 | 30 |
B | A | 3 | 99 |
C | A | 1 | 75 |
D | B | 3 | 183 |
E | C | 2 | 33 |
F | D | 4 | 108 |
G | D,E | 3 | 78 |
H | F | 4 | 96 |
I | G,H | 2 | 61 |
Complete the network diagram/critical path diagram and determine and show the following: -
1. The activities of the critical path.
2. Identify the duration of the project
3. Briefly explain the relationship between the critical path and the project duration showing the importance of the critical path and the implications for project managers.
4.
Complete the Gantt chart showing cash flows on a monthly basis for the duration of the project
Assume costs associated with an activity are incurred equally over the duration of that activity and that each of the activities that are part of the critical path require the full duration to complete. Start tasks not part of the critical path at the earliest possible time.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started