The Gilster Company, a machine tooling firm, has several plants. One plant, located in St. Falls, Minnesota, uses a job order costing system for its
The Gilster Company, a machine tooling firm, has several plants. One plant, located in St. Falls, Minnesota, uses a job order costing system for its batch production processes. The St. Falls plant has two departments through which most jobs pass. Plantwide overhead, which includes the plant managers salary, accounting personnel, cafeteria, and human resources, is budgeted at $400,000. During the past year, actual plantwide overhead was $385,000. Each departments overhead consists primarily of depreciation and other machine-related expenses. Selected budgeted and actual data from the St. Falls plant for the past year are as follows: |
Department A | Department B | |||||
Budgeted department overhead | ||||||
(excludes plantwide overhead) | $ | 153,000 | $ | 439,900 | ||
Actual department overhead | 170,000 | 459,900 | ||||
Expected activity: | ||||||
Direct labor hours | 50,000 | 25,000 | ||||
Machine-hours | 15,000 | 53,000 | ||||
Actual activity: | ||||||
Direct labor hours | 50,500 | 23,900 | ||||
Machine-hours | 15,800 | 55,000 | ||||
For the coming year, the accountants at St. Falls are in the process of helping the sales force create bids for several jobs. Projected data pertaining to job no. 110 are as follows: |
Direct materials | $ | 21,600 | |
Direct labor cost: | |||
Department A (3,000 hr) | 45,000 | ||
Department B (1,100 hr) | 10,000 | ||
Machine-hours projected: | |||
Department A | 230 | ||
Department B | 1,200 | ||
Units produced | 15,000 | ||
1.
Comprehensive Problem 5 Part a
a.1 | Assume the St. Falls plant uses a single plantwide overhead rate to assign all overhead (plantwide and department) costs to jobs. Find the overhead rate by using expected direct labor hours. (Round your answer to 2 decimal places. Omit the "$" sign in your response.) |
Overhead rate | _________$ per direct labor hour |
a.2 | Determine the projected amount of total manufacturing costs per unit for the units in job no. 110. (Round your answer to 2 decimal places. Omit the "$" sign in your response.) |
Manufacturing costs for Job 110 | ____________$ per unit |
2.
Comprehensive Problem 5 Part b
b.1 | Calculate plantwide overhead rate using Machine Hours on projected manufacturing costs for job no. 110. (Round your answer to 2 decimal places. Omit the "$" sign in your response.) |
Plantwide overhead rate | ______$ per machine hour |
b.2 | Calculate two separate department overhead rates using Machine Hours on projected manufacturing costs for job no. 110. (Round your answers to 1 decimal place.Omit the "$" sign in your response.) |
Overhead rateDepartment A | ______$ per machine hour |
Overhead rateDepartment B | ______$ per machine hour |
b.3 | Recalculate the projected manufacturing costs for job no. 110 using three separate rates: one rate for plantwide overhead and two separate department overhead rates, all based on machine-hours. (Round your intermediate calculations and final answer to 2 decimal places. Omit the "$" sign in your response.) |
Total cost | _______$ per unit |
3.
Comprehensive Problem 5 Part c
c.1 | The sales policy at St. Falls dictates that job bids be calculated by adding 27 percent to total manufacturing costs. What would be the bid for job no. 110 using the overhead rate from part a ? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount. Omit the "$" sign in your response.) |
Bid price | $________ |
c.2 | The sales policy at St. Falls dictates that job bids be calculated by adding 27 percent to total manufacturing costs. What would be the bid for job no. 110 using the overhead rate from part b ? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount. Omit the "$" sign in your response.) |
Bid price | $______ |
c.3 | Which of the overhead allocation methods would you recommend ? | ||||
|
4.
Comprehensive Problem 5 Part d
d. | Using the allocation rates in part b, compute the under- or overapplied overhead for the St. Falls plant for the year. (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount. Omit the "$" sign in your response.) |
Overapplied or Underapplied? | $_______ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started