Question
The gross requirements for Items A and H are specified for the beginning of weeks 1 through 8 in the tables that follows. The product
The gross requirements for Items A and H are specified for the beginning of weeks 1 through 8 in the tables that follows. The product structure for the item is given in the figure: The lead time of each item is specified within square brackets. For example, the lead time for Item A is 1 week. Each part requires one unit of constituent parts. For example, one unit of H requires one unit each of J, K, and C. Product Structure for Item A
Item A | ||||||||
---|---|---|---|---|---|---|---|---|
Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | |
Gross Requirement | 0 | 0 | 0 | 0 | 40 | 40 | 50 | 0 |
Item H | ||||||||
---|---|---|---|---|---|---|---|---|
Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | Week 7 | Week 8 | |
Gross Requirement | 0 | 0 | 0 | 0 | 90 | 0 | 115 | 90 |
There is no beginning inventory and there are no scheduled receipts. Determine the planned order releases in for Item C. (First, compute the net requirements and planned order releases for Items A and H. Then determine the gross requirements for the Item C followed by computing its net requirements and planned order releases.) What is planned order release for Item C in Week 3? Specify the number of units. What is planned order release for Item C in Week 4? Specify the number of units.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started