The hierarchical representation of all the tasks in a project is called the _____________. A. work breakdown structure B. internal work product C. Project scope
The hierarchical representation of all the tasks in a project is called the _____________.
A. | work breakdown structure | |
B. | internal work product | |
C. | Project scope | |
D. | Infrastructure |