The hierarchy of project tasks, subtasks, and work packages is a ( n ) : Multiple Choice work package. work breakdown structure. project milestone. activity.
The hierarchy of project tasks, subtasks, and work packages is an:
Multiple Choice
work package.
work breakdown structure.
project milestone.
activity.
statement of work