Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July
The information below was taken from the job cost sheets of Bates Company.
Job Number | Manufacturing Costs as of June 30 | Manufacturing Costs in July | ||||||
101 | $ | 4,100 | ||||||
102 | 3,200 | |||||||
103 | 920 | $ | 2,000 | |||||
104 | 2,100 | 4,500 | ||||||
105 | 5,700 | |||||||
106 | 3,800 | |||||||
During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31.
a. Compute the work in process inventory at June 30.
b. Compute the finished goods inventory at June 30.
c. Compute the cost of goods sold during July.
d. Compute the work in process inventory at July 31.
e. Compute the finished goods inventory at July 31.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started