Question

1 Approved Answer

The information in this paragraph applies to this question and the four questions that follow (so, questions 3-7): A process for making plastic name badges


The information in this paragraph applies to this question and the four questions that follow (so, questions 3-7):

A process for making plastic name badges for Gies students attending iConverge consists of two tasks, Task 1: Molding, followed by Task 2: Polishing. It takes 3 minutes to mold a badge at a Task 1 workstation, and 2 minutes to polish a badge at a Task 2 workstation. There are 2 identical workstations for molding (i.e., 2 badges are molded at the same time) and 1 workstation for polishing.

Based on the information provided, and showing your work including any formula you use, please calculate what is the overall hourly capacity of Task 1: Molding. Please include the units for your response.

Question 4

Based on the information provided, and showing your work including any formula you use, please calculate what is the overall hourly capacity of Task 2: Polishing. Please include the units for your response.

Question 5

Which is the bottleneck task in this badge making process? Please indicate how you identified the bottleneck task.

Question 6

Assuming there is no waiting or inventory of badges in the process, and showing your work, please calculate the throughput time in minutes for a badge to be completed through this process.

Question 7

For this question, ignore all the quantitative information provided earlier and the previous four questions but keep the scenario of the badge making process. Treat thequantitative information provided below as fresh information.

You are given the flow rate of the badge making process to be 24 badges per hour. You are also given the throughput time for a badge to be completed through this two-task process to be 10 minutes. Showing your work, including any formula you use, please calculate how many units of badges would be in the process?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

Is times interest earned meaningful for utilities? Why or why not?

Answered: 1 week ago

Question

Understand the nature of prepaid expenses. E-967

Answered: 1 week ago