The jobs listed below need to be completed. If the jobs are sequenced according to the shortest processing time rule, what is the utilization factor?
The jobs listed below need to be completed. If the jobs are sequenced according to the shortest processing time rule, what is the utilization factor?
Job
Processing Time (days)
Job due date (days)
A B C D E
20 30 10 16 18
180 200 175 230 210
Select one: a. 0.41 b. 0.35 c. 0.39 d. 0.37