The June budget , based on standard costs: Budgeted Production 2,600 pasties Direct materials Dough$286 (0.25 Lbs. @ $0.44/Lb. x 2,600) Filling/spices$936 (0.75 Lbs. @
The June budget, based on standard costs:
Budgeted Production | 2,600 pasties |
Direct materials | Dough$286 (0.25 Lbs. @ $0.44/Lb. x 2,600) Filling/spices$936 (0.75 Lbs. @ $0.48/Lb. x 2,600) Grouper fish--$5,200 (1/16 Lb. @ $32.00/Lb. x 2,600) |
Direct Labor | $2,340 (0.05 DLH@ $18.00/Hr. x 2,600) |
VOH | $1,950 (VOH allocated at $15.00 per DLH x 130 DLH) |
Actual June performance of the central pastie kitchen:
Actual Production | 2,500 pasties |
Direct materials | Dough$315.00 (0.30 Lbs. @ $0.42/Lb. x 2,500) Filling/spices$1,050.00 (0.70 Lbs. @ $0.60/Lb. x 2,500) Grouper fish--$5,460.00 (.91 oz. @ $2.40/oz. x 2,500) |
Direct Labor | $2,337.50 (0.055 DLH@ $17.00/Hr. x 2,500) |
VOH | $1,893.00 |
I need to create a variance analysis. This is the answer that I got for variance analysis but I am not sure of my numbers or the favorable/unfavorable ratings.
Account | Actual Cost | Flexible budget | Total Budget Variance | Price/Rate Variance | Qty/ Efficiency Variance | |||
Dough | $315.00 | $ 275.00 | $40.00 | U | $ 15.00 | F | $ 55.00 | U |
Filling/spices | $1,050.00 | $ 900.00 | $150.00 | U | $ 210.00 | U | $ 60.00 | F |
Grouper fish | $5,460.00 | $ 5,000.00 | $460.00 | U | $ 910.00 | U | $450.00 | F |
Direct labor | $2,337.50 | $ 2,250.00 | $87.50 | U | $ 137.50 | F | $ 225.00 | U |
Variable OH | $1,893.00 | $ 1,875.00 | $18.00 | U | $ 169.50 | U | $ 187.50 | U |
Total | $11,055.50 | $ 10,300.00 | $755.50 | U | $ 1,137.00 | U | $ 42.50 | F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started