The key goal of the WBS is to a. Determine how long a project takes to complete b. provide clear view of project deliverables c.
The key goal of the WBS is to
a. Determine how long a project takes to complete
b. provide clear view of project deliverables
c. identify all of the project work by decomposing deliverables