Question
1 Approved Answer
The labor part of the standard cost is based on Time and motion studies The average time to complete the task including set up and
- The labor part of the standard cost is based on
- Time and motion studies
- The average time to complete the task including set up and downtime
- Both A and B
- Neither A nor B
Use the following information to answer questions 5 through 10
HB Company makes baseball bats. The standard cost of one bat is as follows:
Materials 5 pounds of wood @ $5.00 a pound = $25
Labor .5 hours @ $30 = $15
Overhead .5 hours @ $20 ($15 fixed, $5 variable) = $10
Fixed overhead based on 5,100 normal capacity hours
Total $50
During March, HB produced 10,000 bats and had the following actual costs
Materials 50,100 pounds of wood (cost $245,490, all was used)
Labor 4,900 hours (cost $151,900)
Overhead Total cost $102,900
- HBs March material quantity variance was
- $10,000 favorable
- $1,000 unfavorable
- $500 favorable
- $500 unfavorable
- HBs March material price variance was
- $50,000 favorable
- $500 favorable
- $5,000 favorable
- $5,010 favorable
- HBs March labor quantity (efficiency) variance was
- $30,000 unfavorable
- $3,000 favorable
- $3,000 unfavorable
- $300 favorable
- HBs March labor price (rate) variance was
- $4,900 unfavorable
- $4,900 favorable
- $4,000 unfavorable
- $4,000 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started