The latest finish time of a specific activity is Question 4 options: always equal to the activity's earliest finish time. the same as the latest
The latest finish time of a specific activity is Question 4 options: always equal to the activity's earliest finish time. the same as the latest start time of the activity's predecessors. the latest time the activity can be completed without delaying the project. based upon the project start time and the activity durations