The Leverenz Construction Company began work on a $12,000 contract on 1/1/26. Planned completion was in 2027. The Percentage-of-Completion method is used. Given the following:
The Leverenz Construction Company began work on a $12,000 contract on 1/1/26. Planned completion was in 2027. The Percentage-of-Completion method is used.
Given the following:
|
|
|
| 2026 |
| 2027 |
Costs incurred to date |
|
|
| $4,000 |
| $11,100 |
Estimated costs to complete |
|
|
| 6.000 |
| 0 |
Billings to date |
|
|
| 5,800 |
| 12,000 |
Collections to date |
|
|
| 5,500 |
| 12,000 |
2026 Net Income is: $800
2027 Net Income is: $100
The 12/31/26 balance sheet will show a net CIP/Billings amount of $__________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started