Question
The Mackenzie Oil Co. owns a small field named Lobster, currently producing 11,800 barrels of oil per day. The Operator is considering whether to work-over
The Mackenzie Oil Co. owns a small field named Lobster, currently producing 11,800 barrels of oil per day. The Operator is considering whether to work-over the producing wells in order to improve the performance of the field. The major impact of the work would be to improve productivity in the short term, but at the expense of production in the longer term. Some improvement in overall recovery is also expected.
The work-overs would cost $15 million and could be completed during 2020. As a result of the accelerated production, the field life is expected to be reduced by one year. You are required to advise the management whether to proceed with the planned investment. The current planned and accelerated production profiles and other required information are presented in tables below. These costs are in $2020 terms.
Year
Current Profile
(bopd)
Accelerated Profile
(bopd)
2020
11800
11800
2021
10000
10400
2022
8510
9310
2023
7220
8220
2024
6150
7150
2025
5200
5800
2026
4440
4640
2027
3760
3560
2028
3200
2900
2029
2740
2340
2030
2340
1840
2031
2000
0
Assumptions
Oil Price:
$50.00
Oil Price Escalation Rate:
1.50%
Royalty Rate:
25%
Oil Production Cost per Barrel:
$10.00
Operating Cost Escalation Rate:
1.00%
Income Tax Rate:
30%
Part 2:
The Mackenzie Oil Co. has recently completed its evaluation of a new structure (Juniper) and is satisfied that reserves of oil are sufficient to justify the installation of production facility costing $150 million. Furthermore, management is keen to proceed immediately in order to absorb available cash flow from the company's Aspen Field, which has recently achieved peak production.
A further, adjacent structure, named the Rowan prospect, was discovered last year and has been the target for further seismic investigation. The Exploration Department is optimistic that commercial reserves will be demonstrated in the near future. Management accepts the current assessment that the probability of commercial reserves being identified in the Rowan structure is 35%;
If this oil does exist, the production facility currently planned for Juniper would be inadequate for both reservoirs and, consequently, an expansion in production facility would be required. Alternatively, Mackenzie Oil could decide now to install a larger facility, with capacity for both reservoirs. This option is estimated to cost $225 million.
The drilling rig, Arbor 1, has been leased to drill a single appraisal well on Rowan this year and these results will certainly provide a better indication of the economic potential of the structure. The reliability of this appraisal well is predicted by the company to be around 0.6, meaning that whatever the prognosis, there is a 60% probability that it is correct. If the development decision is delayed until this appraisal result is available, the Juniper program would slip by a year and the company would face a larger short-term tax liability, equivalent to an additional current payment of $35 million. One further well is planned for the Rowan structure next year, but management is not prepared to delay the Juniper decision beyond the result of the first appraisal well.
The Mackenzie Oil management has decided to proceed with the Juniper Field development no later than the completion of the well currently being drilled by Arbor 1. There is, however a problem of deciding whether to proceed with a smaller capacity or to install a larger production facility.
1.Advise the management of Mackenzie Oil as to the optimum strategy in order to minimize the expected cost of the Juniper / Rowan Field development. Note that this requires the construction of a decision tree incorporating the logic of the problem, relevant cost information and probabilities. No revenue information is presented or required.
2.There is some disagreement within the company regarding the probability that Rowan is commercial and management would like advice on the sensitivity of its decision to variation in estimates of the commerciality of the Rowan structure. Investigate the impact of changing this assumption in order to establish the range of values for which the determined optimum strategy remains optimum.
3.A second drilling rig, Arbor 2, may be available now at a very high spot rate. The opportunity therefore exists to bring forward the well planned for next year and to have the information available in time to contribute to the Juniper decision. If the two appraisal wells together on Rowan were considered to provide a reliable assessment, how much extra should Mackenzie Oil be prepared to spend to have this well drilled now rather than next year?
Note that "reliable" in this context means that no matter what the result of the appraisal well, the interpretation provides an accurate assessment of the economic viability of the structure.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started