The management of DGM Marble Manufacturing has identified activity centers to which overhead costs are assigned. The following data are available: Activity Centers Costs Activity
The management of DGM Marble Manufacturing has identified activity centers to which overhead costs are assigned. The following data are available:
Activity Centers | Costs | Activity Drivers |
Utilities | P400,000 | 80,000 machine hours |
Scheduling and Setup | 379,950 | 800 setups |
Material Handling | 828,000 | 1,800,000 pounds of materials |
The companys products and other operating statistics are the following:
| A. Ceramic Tiles | B. Granite Tiles | C. Onyx Tiles |
Prime costs | P120,000 | P130,000 | P150,000 |
Machine hours | 40,000 | 20,000 | 20,000 |
Number of setups | 150 | 400 | 250 |
Pounds of materials | 800,000 | 500,000 | 500,000 |
Number of units produced | 60,000 | 35,000 | 60,000 |
Direct labor hours | 35,000 | 26,000 | 50,000 |
Provide the following based on the procedures of Activity-Based Costing (ABC) system. (2 items x 10 points)
a. Pool rates
b. Overhead cost allocated to each product of DGM Marble Manufacturing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started