Question
The manager, Jenny was recently notifies of the available times for different resources needed (e.g. funds, workers, equiptment suppliers, approval of permits), and also given
The manager, Jenny was recently notifies of the available times for different resources needed (e.g. funds, workers, equiptment suppliers, approval of permits), and also given those jobs that might take a couple of days more/less than normal. With this updated information, she then designed a schedule for the project as shown in Table 4. Make a Gantt chart below to present Jenny's schedule. the time axis in the chart should have the origin of 10/1/2020.Your chart should be linked to the data in Table 4 on this worksheet, not a picture or image created somewhere else.
Table 4 -- Jenny's schedule | |||
Job label | Job description | Start date | End date |
A | Planning | 10/8/2020 | 10/10/2020 |
B | Purchasing | 10/11/2020 | 10/18/2020 |
C | Excavation | 10/10/2020 | 10/19/2020 |
D | Sawing | 10/20/2020 | 10/23/2020 |
E | Placement | 10/24/2020 | 10/26/2020 |
F | Assembly | 10/26/2020 | 10/28/2020 |
G | Infill | 10/28/2020 | 10/30/2020 |
H | Outfill | 10/29/2020 | 10/31/2020 |
I | Decoration | 11/1/2020 | 11/4/2020 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started