Question

1 Approved Answer

The manager, Jenny was recently notifies of the available times for different resources needed (e.g. funds, workers, equiptment suppliers, approval of permits), and also given

The manager, Jenny was recently notifies of the available times for different resources needed (e.g. funds, workers, equiptment suppliers, approval of permits), and also given those jobs that might take a couple of days more/less than normal. With this updated information, she then designed a schedule for the project as shown in Table 4. Make a Gantt chart below to present Jenny's schedule. the time axis in the chart should have the origin of 10/1/2020.Your chart should be linked to the data in Table 4 on this worksheet, not a picture or image created somewhere else.

Table 4 -- Jenny's schedule

Job label Job description Start date End date
A Planning 10/8/2020 10/10/2020
B Purchasing 10/11/2020 10/18/2020
C Excavation 10/10/2020 10/19/2020
D Sawing 10/20/2020 10/23/2020
E Placement 10/24/2020 10/26/2020
F Assembly 10/26/2020 10/28/2020
G Infill 10/28/2020 10/30/2020
H Outfill 10/29/2020 10/31/2020
I Decoration 11/1/2020 11/4/2020

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Payroll

Authors: Steven M. Bragg

1st Edition

0471251089, 9780471251088

More Books

Students also viewed these Accounting questions

Question

Find the limit. sin x - sin x cos x lim .2

Answered: 1 week ago