Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The

The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows:

Immediate Time (weeks)
Activity Description Predecessor(s) Optimistic Most Probable Pessimistic
A Meet with board 1 1 3
B Hire coaches A 2 4 6
C Reserve pool A 2 6 10
D Announce program C 1 2 3
E Meet with coaches B, C, F 1 4 7
F Order team suits A 1 2 3
G Register swimmers D, E 1 3 5
H Collect fees G 1 2 3
I Plan first practice E, F, H 1 1 1
  1. Which project network is correct?

image text in transcribed

  1. Develop an activity schedule. If required, round your answers to two decimal places. If your answer is zero enter 0.
    Activity Expected Time Variance
    A
    B
    C
    D
    E
    F
    G
    H
    I
    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity
    A
    B
    C
    D
    E
    F
    G
    H
    I
  2. What are the critical activities, and what is the expected project completion time? Critical Path: Expected project completion time = fill in the blank 75 weeks.
  3. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks) based solely on the critical path? Should the manager begin planning the swimming program before February 1? fill in the blank 76. If necessary, round your answer to two decimal places. Using the normal distribution, z = fill in the blank 77. If necessary, round your answer to two decimal places. If negative answer is required, enter the minus sign before the number. Probability of 13 weeks or less is fill in the blank 78. If necessary, round your answer to four decimal places. Note: Use Appendix B to identify the probability. With this probability, the manager should start .
a. Which project network is correct? (0) Start AKB Finish Start A Finish (iv) Start A Start A Finish a. Which project network is correct? (0) Start AKB Finish Start A Finish (iv) Start A Start A Finish

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Economics Of Financial Markets

Authors: Roy Bailey

1st Edition

051111415X, 9780511114151

More Books

Students also viewed these Finance questions

Question

What is one of the skills required for independent learning?Explain

Answered: 1 week ago