The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The
The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows:
Immediate | Time (weeks) | ||||
Activity | Description | Predecessor(s) | Optimistic | Most Probable | Pessimistic |
A | Meet with board | 1 | 1 | 3 | |
B | Hire coaches | A | 2 | 4 | 6 |
C | Reserve pool | A | 2 | 6 | 10 |
D | Announce program | C | 1 | 2 | 3 |
E | Meet with coaches | B, C, F | 1 | 4 | 7 |
F | Order team suits | A | 1 | 2 | 3 |
G | Register swimmers | D, E | 1 | 3 | 5 |
H | Collect fees | G | 1 | 2 | 3 |
I | Plan first practice | E, F, H | 1 | 1 | 1 |
- Which project network is correct?
- Develop an activity schedule. If required, round your answers to two decimal places. If your answer is zero enter 0.
Activity Expected Time Variance A B C D E F G H I Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity A B C D E F G H I - What are the critical activities, and what is the expected project completion time? Critical Path: Expected project completion time = fill in the blank 75 weeks.
- If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks) based solely on the critical path? Should the manager begin planning the swimming program before February 1? fill in the blank 76. If necessary, round your answer to two decimal places. Using the normal distribution, z = fill in the blank 77. If necessary, round your answer to two decimal places. If negative answer is required, enter the minus sign before the number. Probability of 13 weeks or less is fill in the blank 78. If necessary, round your answer to four decimal places. Note: Use Appendix B to identify the probability. With this probability, the manager should start .
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started