Question
The Manoli Company has collected the following data for use in calculating product costs: Activity Data: (expected and actual) Rug Cleaners Sweepers Total Units Produced
The Manoli Company has collected the following data for use in calculating product costs: Activity Data: (expected and actual)
Rug Cleaners | Sweepers | Total | |
Units Produced | 50,000 | 250,000 | 300,000 |
Prime Costs | $200,000 | $750,000 | $950,000 |
Direct Labor Hours | 10,000 | 40,000 | 50,000 |
Machine Hours | 20,000 | 10,000 | 30,000 |
Number of Setups | 25 | 75 | 100 |
Inspection Hours | 1200 | ,2,800 | 4,000 |
Number of Moves | 140 | 210 | 350 |
Departmental Data: (expected and actual)
Molding | Assembly | Total | |
Direct Labor Hours | |||
Rug Cleaners | 5,000 | 5,000 | 10,000 |
Sweepers | |||
Total | 10,000 | 40,000 | 50,000 |
Machine Hours | |||
Rug Cleaners | 17,000 | 3,000 | 20,000 |
Sweepers | 3,000 | 7,000 | 10,000 |
Total | 20,000 | 10,000 | 30,000 |
Overhead Costs | |||
Machining | $120,000 | $30,000 | $150,000 |
Moving Materials | 40,000 | 30,000 | 70,000 |
Setting Up | 70,000 | 10,000 | 80,000 |
Inspecting Products | 20,000 | 30,000 | 50,000 |
Total | $250,000 | $100,000 | $350,000 |
What is the activity rate for moving materials?
a. | $1000 | |
b. | 0.2 | |
c. | $200 | |
d. | $800 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started