The manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours.

The manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost PoolActivity MeasureEstimated Overhead CostExpected

ActivityMachiningMachine-hours$203,00010,000MHsMachine setupsNumber of setups$121,900230setupsProduction designNumber of products$87,0002productsGeneral factoryDirect labor-hours$379,50015,000DLHs

Activity MeasureProduct YProduct ZMachining8,3001,700Number of setups50180Number of products11Direct labor-hours9,5005,500

14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?(Round your answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles

Authors: Jerry J Weygandt

10th Edition

1118009282, 9781118009284

More Books

Students also viewed these Accounting questions

Question

What is the cerebrum?

Answered: 1 week ago