Question
1 Approved Answer
The materials price variance is computed by multiplying the difference between the actual price and the standard price by the actual quantity of materials purchased.
The materials price variance is computed by multiplying the difference between the actual price and the standard price by the actual quantity of materials purchased. True False
Step by Step Solution
There are 3 Steps involved in it
Step: 1