The Miller Company manufactures and sells industrial components. The Christo plant is responsible for producing two components, AD-5 and FX-3. Plastic, brass, and aluminum are
The Miller Company manufactures and sells industrial components. The Christo plant is responsible for producing two components, AD-5 and FX-3. Plastic, brass, and aluminum are used in the production of these two products.
The Miller Company has adopted a 13-period reporting cycle in all of its plants for budgeting purposes. Each period is four weeks long and has 20 working days. Experience has shown that adequate inventory levels for AD-5 and FX-3 can be maintained if 40% of the next periods projected sales are on hand at the end of a reporting period. Based on this experience and the projected sales, the Christo plant has budgeted production of 8,000 units of AD-5 and 6,000 units of FX-3 in the eighth period. Production is assumed to be uniform for both products within each four-week period.
The raw material specifications for AD-5 and FX-3 are as follows:
AD-5 (kilograms) | FX-3 (kilograms) | |||||
Plastic | 2.0 | 1.0 | ||||
Brass | 0.5 | |||||
Aluminum | 1.5 | |||||
|
Data relating to the purchase of raw materials are as follows:
Projected Inventory Status at the End of the Seventh Period (kilograms) | ||||||||||||||||||
| ||||||||||||||||||
Purchase Price per Kilogram | Standard Purchase Lot (kilograms) | Reorder Point (kilograms) | On Hand | On Order | Lead Time in Working Days | |||||||||||||
Plastic | $ | 0.40 | 15,000 | 12,000 | 16,000 | 15,000 | 10 | |||||||||||
Brass | 0.95 | 5,000 | 7,500 | 9,000 | 30 | |||||||||||||
Aluminum | 0.55 | 10,500 | 10,000 | 14,000 | 10,000 | 20 | ||||||||||||
|
The sales of AD-5 and FX-3 vary somewhat from month to month. However, the safety stock incorporated into the reorder point for each of the raw materials is adequate to compensate for variations in the sales of the finished products.
Raw material orders are placed the day the quantity on hand falls below the reorder point. Christo plants suppliers are very dependable, so the given lead times are reliable. The outstanding orders for aluminum and plastic are due to arrive on the fourth and tenth working days of the eighth period, respectively. Payments for all raw material orders are remitted in the month of delivery.
Required: The Christo plant is required to submit a report to Miller Company corporate headquarters, summarizing the projected raw materials activities, before each period commences. The data for the eighth-period report are being assembled. Determine the following items for plastic, brass, and aluminum for inclusion in the eighth-period report:
1. Projected quantities (in kilograms) of each raw material to be issued to the Production Department.
|
2.&3. Projected quantities (in kilograms) of each raw material ordered and the date (in terms of working days) the order is to be placed. The projected inventory balance (in kilograms) of each raw material at the end of the period.
|
4. The payments for purchases of each raw material.
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started