Question

1 Approved Answer

The MobileGo project is making progress implementing the new systems. However, the software upgrades and the new software installation are not complete. The project sponsor

The MobileGo project is making progress implementing the new systems. However, the software upgrades and the new software installation are not complete. The project sponsor has requested an update on the project. Using the MobileGo Earned Value scenario spreadsheet , complete the following tasks.

  1. Complete earned value metrics for each line item of the project.
  2. Use the metrics to create indexes for cost and schedule.
  3. Explain what the metrics mean in terms of the overall health of the project.
  4. Project where the project will end in terms of budget and schedule. What potential risks and trade-offs do you see?
  5. Explain any recommendations you have for improving the project schedule, budget, or both.

Make a 10-slide PowerPoint presentation that you can give to the project sponsor that explains your calculations, predictions, and recommendations. Remember that you are giving this information to the project sponsor, so consider what he or she would need to know as you draft your presentation.

Use at least one outside source to support your recommendations for improvement.

You must either use speaker notes or audio to fully explain your slides. Be sure to elaborate in your speaker notes or audio; do not simply repeat the text from your slides.


Step by Step Solution

3.40 Rating (169 Votes )

There are 3 Steps involved in it

Step: 1

Task 1 Complete Earned Value Metrics Use the MobileGo Earned Value scenario spreadsheet to fill in t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions

Question

=+b. What are the penalties for exceeding the upper specification?

Answered: 1 week ago

Question

=+a. The number of flaws per square foot in a large sheet of metal

Answered: 1 week ago