The monthly production schedule of the bicycle manufacturer is given below. Week Model one 2 3 4 B210 50 one hundred 200 150 G210 50

The monthly production schedule of the bicycle manufacturer is given below.
Week
Model
one
2
3
4
B210
50
one hundred
200
150
G210
50
one hundred
200
150
B203
15
30
60
45
G203
15
30
60
45
B201
20
40
80
60
G201
20
40
80
60
The critical work center in the production of these bicycles is the welding center. The effectiveness of this center is 95 percent and its utilization is 90 percent. The time (in hours) required by each bike model in this center is given below:
B210
G210
B203
0.20
0.22
0.15
G203
B201
G201
0.17
0.07
0.09
Assume that the work center is available 40 hours a week. Calculate the weekly capacity and loading percentage of the work center and draw the weekly load profile.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the weekly capacity and loading percentage of the welding center we need to follow thes... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Precalculus

Authors: Michael Sullivan

9th edition

321716835, 321716833, 978-0321716835

More Books

Students also viewed these Finance questions

Question

5. What is the contribution of prep activities ahead of workshops?

Answered: 1 week ago

Question

8. What is the role of reflection?

Answered: 1 week ago