The Morgan Company's April budget called for labor costs of $125,000. Because the actual labor costs were exactly $125,000, management concluded there were no labor
The Morgan Company's April budget called for labor costs of $125,000. Because the actual labor costs were exactly $125,000, management concluded there were no labor variances. Comment on the manager's conclusion.