The Mowry Machine Shop still has five jobs to be processed as of 8 A . M . today ( day 2 7 ) at

The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today(day 27) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival.
Job
Time Since
Order Arrived
(days ago)
Processing
Time(days)
Due Date
(days from
now)
A
12
4
15
B
10
4
12
C
5
3
26
D
3
10
18
E
1
8
9
a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due.
Part 2
Using the FCFS(first come, first served) decision rule for sequencing the jobs, the order is:
Sequence
1
2
3
4
5
Job
C
A
D
E
B
C
E
D
B
A
A
C
E
D
B
D
E
B
A
C

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions

Question

=+b) Compute the x2 statistic.

Answered: 1 week ago

Question

How does selection differ from recruitment ?

Answered: 1 week ago