Question
1 Approved Answer
The MRP gross requirements for item A are shown here for the next 1 0 weeks. Lead time for A is three weeks and setup
The MRP gross requirements for item A are shown here for the
next weeks. Lead time for A is three weeks and setup cost is
$ There is a carrying cost of $ per unit per week. Beginning
inventory is units.
Use the least total cost or the least unit cost lotsizing method to
determine when and for what quantity the first order should be
released.