The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $12. There is a carrying cost of $0,015 per unit per week. Beginning inventory is 80 units. Use the least total cost and the least unit cost lot-sizing method to determine what quantity the first order should be released and for which period
Step by Step Solution
There are 3 Steps involved in it
Step: 1