The network diagram for a project has the following three paths Path Mean Duration Variance 1 55 5 2 47 7 3 54 10 4
The network diagram for a project has the following three paths
Path | Mean Duration | Variance |
---|---|---|
1 | 55 | 5 |
2 | 47 | 7 |
3 | 54 | 10 |
4 | 22 | 3 |
The network diagram for a project has the following three paths Path Mean Duration Variance 1 55 5 2 47 7 3 54 10 4 22 3 What is the likelihood that the project will complete in 60 time units or less? Select the nearest percentage. [Recommended time: