1 Approved Answer
The network for a small project with six activities is given below. The duration of the activities and the manpower requirement for the individual activities
The network for a small project with six activities is given below. The duration of the activities and the manpower
requirement for the individual activities are also given in the figure. The manpower availability has a ceiling of on
any day. Arrive at a suitable resource allocation schedule with minimum possible project duration.