Question

1 Approved Answer

The new president of Miskatonic University has decided on building a pool. She sat down with the contractor and together they determined what activities

The new president of Miskatonic University has decided on building a pool. She sat down with the contractor and together they determined what activities would have to occur, their precedence relationships, and estimated durations (in weeks). However, after a review it appeared that construction would interfere with the start of the Fall semester. Miskatonic asked the contractor to present time and cost estimates for crashing the project. The data are listed below. Activity A B C D E F G H I Predecessor - A A A B B C D F, G E, I, H Normal Time 6 3 9 10 4 2 12 3 14 4 What activity has the greatest weekly cost for crashing? Crash Time 4 1 6 8 2 1 9 2 10 3 Normal Cost/Week $200 $350 $450 $800 $750 $900 $875 $500 $375 $600 Crash Cost/Week $450 $600 $800 $1,100 $1,250 $2.000 $1,750 $900 $600 $1,000

Step by Step Solution

3.32 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

Activity F has the greatest weekly crashing cost Formula for cost slope Crashing c... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting

Authors: Thomas Beechy, Umashanker Trivedi, Kenneth MacAulay

6th edition

013703038X, 978-0137030385

More Books

Students also viewed these General Management questions

Question

What are some ways firms get ideas for capital projects?

Answered: 1 week ago