Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The next project is the construction of a residential building. Enter the project bask, duration, and resources, taking inso account subsequent tasks in each task

image text in transcribed
image text in transcribed
The next project is the construction of a residential building. Enter the project bask, duration, and resources, taking inso account subsequent tasks in each task as ahown below. using Mirrosofl Project. Enter them by column to see more suggested effects. Enter the appropriate resourees for each of these tasks (peopect manager, site enginser. 20 workers, drilling equipment, cutting equipment, etc.). Vse the first day of the following month as the project start date. Take the folloning in account: 1. Enter the dasa up inte an MS project file. 2. Create a new Calendar which in the days Friday and Saturday are non-works, and the other workdays, works start from 8.00 ant $6.00pm with a break at 1.00pm. 3. Put Nuto schedale as a task mode for all tasks, 4. Link between tasks with saitable relationships and shors then in a sew colume (Type). 5. Add note on task (Decide data \& venue to sign agreement): launch with Project team and Partners. 6. Add Resources in Resource shoet, with max availability I and std. rale for work Resourtes between 56000$2000. 7. Make movement between Resource shee \& Gant chart very easy. 8. Assign Resourees to tasks, and add some aew columns (Resources name 8 Codi) in Gant chart window. 1. Enter the data up into an MS project file. 2. Create a new Calendar which in the days Friday and Saturday are non-works. and the other workdays, works start from 8:00 am to 6:00pm with a break at 1:00 pm. 3. Put Auto schedule as a task mode for all tasks. 4. Link between tasks with suitable relationships and show them in a new column (Type). 5. Add note on task (Decide data \& venue to sign agreement): launch with Project team and Partners. 6. Add Resources in Resource sheet, with max availability 1 and std. rate for work Resources between $600 - $2000. 7. Make movement between Resource sheet \& Gantt chart very easy. 8. Assign Resources to tasks, and add some new columns (Resources name \& Cost) in Gantt chart window. 9. Make Work hour for all tasks steady. 10. Customize a Gantt Chart view . 11. Add some the task to time line view. The next project is the construction of a residential building. Enter the project bask, duration, and resources, taking inso account subsequent tasks in each task as ahown below. using Mirrosofl Project. Enter them by column to see more suggested effects. Enter the appropriate resourees for each of these tasks (peopect manager, site enginser. 20 workers, drilling equipment, cutting equipment, etc.). Vse the first day of the following month as the project start date. Take the folloning in account: 1. Enter the dasa up inte an MS project file. 2. Create a new Calendar which in the days Friday and Saturday are non-works, and the other workdays, works start from 8.00 ant $6.00pm with a break at 1.00pm. 3. Put Nuto schedale as a task mode for all tasks, 4. Link between tasks with saitable relationships and shors then in a sew colume (Type). 5. Add note on task (Decide data \& venue to sign agreement): launch with Project team and Partners. 6. Add Resources in Resource shoet, with max availability I and std. rale for work Resourtes between 56000$2000. 7. Make movement between Resource shee \& Gant chart very easy. 8. Assign Resourees to tasks, and add some aew columns (Resources name 8 Codi) in Gant chart window. 1. Enter the data up into an MS project file. 2. Create a new Calendar which in the days Friday and Saturday are non-works. and the other workdays, works start from 8:00 am to 6:00pm with a break at 1:00 pm. 3. Put Auto schedule as a task mode for all tasks. 4. Link between tasks with suitable relationships and show them in a new column (Type). 5. Add note on task (Decide data \& venue to sign agreement): launch with Project team and Partners. 6. Add Resources in Resource sheet, with max availability 1 and std. rate for work Resources between $600 - $2000. 7. Make movement between Resource sheet \& Gantt chart very easy. 8. Assign Resources to tasks, and add some new columns (Resources name \& Cost) in Gantt chart window. 9. Make Work hour for all tasks steady. 10. Customize a Gantt Chart view . 11. Add some the task to time line view

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing For Dummies

Authors: Maire Loughran

1st Edition

0470530715, 978-0470530719

More Books

Students also viewed these Accounting questions

Question

Explain the process of MBO

Answered: 1 week ago

Question

What is meant by a green or sustainable strategy?

Answered: 1 week ago