Question

1 Approved Answer

The normal capacity of the Malloy Company is 20,000 direct labor hours and 10,000 units per month.A finished unit requires 15 pounds of materials at

The normal capacity of the Malloy Company is 20,000 direct labor hours and 10,000 units per month.A finished unit requires 15 pounds of materials at an estimated cost of $1.00 per pound.The estimated cost of labor is $12.00 per hour.It is estimated that overhead for a month will be $15,000.

During the month of June, 19,000 direct labor hours were worked at an average rate of $11.50 an hour.The number of units produced was 9,000, using all 132,000 pounds of material that were purchased at a cost of $1.05 per pound.

a.

Make a standard cost summary showing the standard unit cost.

b.

Calculate the material and labor variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

a Standard Data of Materials for actual output Material required per pound 15 pounds Standard materi... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Cost Accounting

Authors: Edward J. Vanderbeck, Maria Mitchell

17th edition

9781305480520, 1305087402, 130548052X, 978-1305087408

More Books

Students also viewed these Accounting questions

Question

What is a social class system?

Answered: 1 week ago