Question

1 Approved Answer

The normal cost for an activity is $ 7 , 0 0 0 and the crash cost is $ 1 2 , 0 0 0

The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
$1000
$1250
$2000
$2500
None of the above
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions