Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Northwest Ohio Little Theater is planning its first play for the upcoming season. However, due to the illness of one of their key board

The Northwest Ohio Little Theater is planning its first play for the upcoming season. However, due to the illness of one of their key board members, the project is behind schedule. Their President, John Brown, has taken MGMT 3000 at BGSU before. He has come up with a list of activities, their normal time requirements, and their sequence. He also knows the shortest completion time for each activity and the extra cost to expedite each activity. John found that they would not have enough time to make the performance date if they follow the normal schedule as outlined below. Help John to sort things out and solve the problem. You need to draw the network, complete the Critical Path Method calculation, and crash the project. Answer Questions 10-19. What is the critical path before John crashes the project? Table 1. Activities and Information Activity A B C E G H Normal Time Crash Time Immediate (weeks) (weeks) 10 2 4 4 10 8 2 12 2 2 2 3 8 6 8 Table 2. Project Crashing Steps Predecessor A B B C C,D D D E,F,H G,I Normal Cost $5,000 $3,000 $5,000 $6,000 $750 $3,000 $4,000 $5,000 $1,000 $2,000 Crash $7,500 Cost $8,000 $10,000 $2,250 $3,000 Expediting Crash Cost per Week Opportunities
image text in transcribed
image text in transcribed
The Northwest Ohio Little Theater is planning its first play for the upcoming season. However, due to the illness of one of their key board members, the project is behind schedule. Their President, John Brown, has taken MGMT 3000 at BGSU before. He has come up with a list of activities, their normal time requirements, and their sequence. He also knows the shortest completion time for each activity and the extra cost to expedite each activity. John found that they would not have enough time to make the performance date if they follow the normal schedule as outlined below. Help John to sort things out and solve the problem. You need to draw the network, complete the Critical Pakh Method calculation, and crash the project. Answer Questions 10-19. What is the critical path before John crashes the project? Table 1. Activities and Information \begin{tabular}{l} \hline Dediting Crash \\ st per Week Opportunities \\ \hline \end{tabular} Table 2. Project Crashing Steps How long will it take to complete the project before you help John crash the project? 30 32 29 28 31 Question 12 0/1 pts What is the slack time of activity G? 2. 12 0 10 None of the choices are correct

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

Chinese 1st Edition

7508679814, 978-7508679815

More Books

Students also viewed these General Management questions