The Oakland plant has the following overhead cost estimates for the coming year: Machine maintenance related costs $ 240,000 Set-up related costs 200,000 Inspection related
The Oakland plant has the following overhead cost estimates for the coming year: | ||||||||
Machine maintenance related costs | $ 240,000 | |||||||
Set-up related costs | 200,000 | |||||||
Inspection related costs | 500,000 | |||||||
Total overhead | $ 940,000 | |||||||
Overhead is currently applied using labor hours, with an expected amount | ||||||||
of 100,000 hours in the next year. | ||||||||
Total expected machine hours | 60,000 | hours | ||||||
Total expected set-ups | 800 | set-ups | ||||||
Total expected inspections | 4,000 | inspections | ||||||
The following data has been assembled for a proposed job which would require the | ||||||||
production of 1,000 units of a product. Bid prices normally reflect a 20% mark-up on cost. | ||||||||
Proposed Job | ||||||||
Production | 1,000 | units | ||||||
Direct material | $ 10,000 | |||||||
Direct labor hours | 1,000 | hours | ||||||
Direct labor rate | $ 12.00 | per hour | ||||||
Machine hours | 900 | hours | ||||||
Batch size | 250 | units per batch | ||||||
Number of inspections | 8 | inspections | ||||||
a. Determine the bid price for the proposed job using the current costing system. (8 pts) | ||||||||
b. Determine the bid price for the proposed job using an activity-based costing system. (8 pts) |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started