The operations director of a local construction company asks a section manager to propose a work schedule for an upcoming construction project. Details of seven

The operations director of a local construction company asks a section manager to propose a work schedule for an upcoming construction project. Details of seven key tasks are as follows:

Task Immediate predecessor Time (calendar days)
P - 138
Q P 69
R P 161
S R 46
T Q, D 92
U S 69
V T, U 161

(a) Derive the project network diagram and compute all key dates including ES, LS, EF and LF. Deduce the critical path and the earliest completion time. (25 marks) ES: Early Start / EF: Early Finish / LS: Late Start / LF: Late Finish

(b) By deploying specialised equipment for the above project, the completion time of task Q could be shortened by 3 weeks. Discuss what the operations director should or should not do to speed up the construction project completion as a whole. (25 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel, Scott M. Shafer

9th edition

1118947029, 978-1119031963, 1119031966, 978-1118947029

More Books

Students also viewed these General Management questions