Question
The operations director of a local construction company asks a section manager to propose a work schedule for an upcoming construction project. Details of seven
The operations director of a local construction company asks a section manager to propose a work schedule for an upcoming construction project. Details of seven key tasks are as follows:
Task | Immediate predecessor | Time (calendar days) |
P | - | 138 |
Q | P | 69 |
R | P | 161 |
S | R | 46 |
T | Q, D | 92 |
U | S | 69 |
V | T, U | 161 |
(a) Derive the project network diagram and compute all key dates including ES, LS, EF and LF. Deduce the critical path and the earliest completion time. (25 marks) ES: Early Start / EF: Early Finish / LS: Late Start / LF: Late Finish
(b) By deploying specialised equipment for the above project, the completion time of task Q could be shortened by 3 weeks. Discuss what the operations director should or should not do to speed up the construction project completion as a whole. (25 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started