The Osprey Laboratory just finished its operations for September. September was a particularity busy month due to a chemical spill and required an increase in lab testing. As a consequence, the laboratory collected and processed more laboratory samples than planned for the month. The actual costs and the budgeted costs for the month are included below.
Osprey Medical Laboratory Cost Control Report For the Month Ended September 30 | ||
| Actual | Static Budget |
Laboratory samples collected | 920 | 700 |
|
|
|
Variable costs: |
|
|
Medical supplies | $14,878 | $10,640 |
Lab tests | 15,389 | 12,915 |
Refreshments for staff and volunteers | 1,779 | 1,435 |
Administrative supplies | 284 | 490 |
Total variable costs | 32,330 | 25,480 |
|
|
|
Fixed costs: |
|
|
Staff salaries | 19,800 | 19,800 |
Equipment depreciation | 2,250 | 2,250 |
Rent | 3,150 | 2,850 |
Utilities | 486 | 450 |
Total fixed cost | 25,686 | 25,350 |
Total cost | $58,016 | $50,830 |
Required:
- Prepare a comprehensive performance report for September. (32 marks)
- What is the overall Static Budget variance? Explain the variance by evaluating the Flexible Budget Variance and the Sales Volume Variance. (3 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started