the overhead costs at various levels of activity for Joey's Timber Company are as follows: Month Machine Hours Total Overhead Costs July 40,000 $ 186,200

the overhead costs at various levels of activity for Joey's Timber Company are as follows:

Month Machine Hours Total Overhead Costs

July 40,000 $ 186,200

August 60,000 $ 210,500

September 80,000 $ 260,000

October 50,000 $ 198,400

Total overhead costs are made up of electricity, depreciation of equipment and maintenance. The breakdown of these costs at the 40000 machine hour level of activity is:

Electricity (variable) $ 56,000

Depreciation of equipment (fixed) 65,000

Maintenance (mixed) 65,200

Total Overhead Costs $186,200

Joey needs to breakdown the maintenance cost into the fixed and variable components.

1. From the information above, estimate how much of September's overhead cost is made up by the maintenance cost.

2. Using the high-low method, estimate a cost formula for maintenance

3. Express the total overhead costs in the linear equation form Y = a + bX

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Carl S Warren, James M Reeve, Jonathan Duchac

12th Edition

0538478519, 9780538478519

More Books

Students also viewed these Accounting questions

Question

1. Describe the Good Lives Model of offender rehabilitation

Answered: 1 week ago

Question

8. How can an interpreter influence the message?

Answered: 1 week ago

Question

Subjective norms, i.e. the norms of the target group

Answered: 1 week ago